Feasibility gate
No irreversible bronze spend until legal/environmental feasibility and a credible deployment path exist.
A provisional working budget for sculpture, engineering, freight, a long-range vessel, documentation and the contingency demanded by trying to carry a large bronze Great Old One to the least convenient address on Earth.
The £150,000 vessel allowance remains a planning figure pending real charter quotations. The 18-22 day voyage model should be put to operators before launch; if credible quotations materially exceed it, the public target must change rather than pretending the Pacific can be negotiated with.
The ship allowance is not merely cabin accommodation. It must cover a vessel capable of the range, crew, fuel, operational days, deck handling, communications, safety systems and support for the deployment. Port costs, unusual lift requirements and schedule extensions may be quoted separately.
For that reason, the current £350,000 total is a working target, not a promise that the expedition can be delivered for exactly that figure.
The full campaign target is currently approximately £350,000, but the project does not depend on treating that figure as an all-or-nothing threshold.
Funds raised at lower levels would support the work appropriate to that stage. The key principle is simple: money becoming available does not, by itself, authorise the next irreversible commitment.
Feasibility, legal and environmental advice, engineering studies, foundry consultation, vessel enquiries and insurance discussions.
Final design, detailed engineering and fabrication only if the legal, environmental and operational work still supports the project.
Vessel, freight, port, deployment and insurance commitments only when the project has real supplier prices and sufficient funds to proceed responsibly.
The final expedition should not be contracted until the project has an executable plan, adequate insurance, appropriate permissions and enough contingency to avoid relying on optimism as a marine safety system.
The project would complete and publish the stages that can responsibly be funded. If the full expedition later proves technically, legally or financially impracticable, the project will publish what was raised, what was spent, what work was completed, what remains unspent and what realistic options remain.
The supporter programme proposes up to six civilian places at £30,000 each. If all six are sold, gross receipts would be £180,000. Those receipts should not simply disappear into the headline crowdfunding number.
The preferred accounting treatment is to publish them separately and apply them primarily against passenger-related and vessel costs. Once contracts are signed, the campaign budget can be revised to show whether berth income reduces the net amount required from donations or instead covers an expanded/safer vessel specification.
The project advances in stages. Early money should buy information and engineering before it buys irreversible bronze.
Legal/environmental scoping, engineering feasibility, foundry discussions and vessel market enquiries.
Develop the approved sculpture, mass model, lifting concept, preliminary deployment method and serious supplier quotations.
Principal sculpture fabrication can begin once legal and operational assumptions are sufficiently mature.
Vessel negotiations, insurance, port logistics and deployment hardware move from estimates to commitments.
The expedition should be close to contractable, subject to final permissions and updated vessel pricing.
Present working target, including contingency. If quotations show it is inadequate, the budget will be revised publicly.
Major quotations, material budget revisions and principal commitments should be published as the project develops. A simple public change log can show the date, reason and effect of each revision.
Project expenditure should be tracked by category, with GoFundMe receipts distinguished from separate commercial receipts such as expedition berths. Any material unused contingency should be disclosed with the final accounts and its proposed treatment explained.
No irreversible bronze spend until legal/environmental feasibility and a credible deployment path exist.
No vessel commitment until the project has adequate funds, insurance and an executable lift/deployment plan.
Publish principal costs, berth receipts, remaining contingency and the final project archive.